Footing Calculator

Concrete Footing Calculator: Cubic Yards for Any Footing

Free Footing Calculator

Calculate Cubic Yards for Your Footing

Enter the total length, width and depth of your footing. This works as a concrete wall calculator too: enter the wall thickness as the width and the wall height as the depth. The concrete footing calculator returns cubic yards, a recommended order size rounded up to the next quarter yard, and a bag count if you plan to mix it yourself.

0.00 cubic yards
Order 0.00 yd³  rounded up to the next quarter yard
Mixing it yourself?
Read this to dispatch

Estimates only. Confirm yardage, strength and slump with dispatch before you pour. Short loads are available so a small job is not billed as a full truck.

Measuring

How to Measure a Concrete Footing

Start with the total length of the footing, sometimes called a footer, in feet. Add up every run, including corners, returns and any stepped sections or piers poured at the same time. For a house or garage foundation, that is the full perimeter plus any interior bearing lines.

Next, measure the width and depth of the trench in inches, not the width of the wall that will sit on it. Check at a few points, because a machine-dug trench is often wider than planned and the extra width takes extra concrete. The concrete footing calculator multiplies length by width by depth, then divides by 27 to get cubic yards.

Finally, leave the 10 percent waste box checked. It covers over-dig, an uneven trench bottom and spillage. If your contractor has already added a margin to the plan, uncheck it so you are not ordering twice. The concrete footing calculator works the same way for any footing or wall.

New homes under construction in Georgia where each footing is sized with a concrete footing calculator

Quick Reference

Concrete Footing Yardage by Size and Length

These figures are cubic yards to order for a continuous footing. They include a 10 percent allowance for waste and are rounded up to the next quarter yard, which is how an order is billed. Use them for a first estimate, then enter your exact numbers in the concrete footing calculator above.

Footing size (width x depth)50 ft long100 ft long150 ft long
12 x 8 in1.502.754.25
16 x 8 in2.003.755.50
18 x 10 in2.755.257.75
20 x 10 in3.005.758.50
24 x 12 in4.258.2512.25
30 x 12 in5.2510.2515.50

A full truck carries 9 to 10 cubic yards, so a 24 by 12 inch footing that runs 150 feet needs more than one load. Anything 7 yards or less is a short load, covered on our short load concrete delivery page.

Concrete pump truck placing a footing pour on a Georgia job site

Footing Size

How Wide and How Deep Should a Footing Be?

Footing size depends on the load it carries and the soil under it, so there is no single answer. A common rule of thumb is a footing about twice as wide as the wall it supports. A light wall or shed may use something near 12 by 8 inches, while a house foundation is usually wider and deeper. Your plans or engineer set the real numbers.

Depth below grade matters too. Footings generally need to reach below the frost line and sit on undisturbed soil, and your local building department sets the minimum for your county. Confirm it before you dig, and schedule any required inspection before the concrete arrives so the truck is not left waiting.

Tell dispatch the strength in psi that your plans call for. If you are not sure, ask your builder or engineer, then call us to confirm the mix. Size changes yardage quickly: on a 100 foot run, going from a 16 by 8 inch footing to a 24 by 12 inch footing takes the order from 3.75 to 8.25 yards. For general reference, see the National Ready Mixed Concrete Association.

Bags or Ready Mix

Bagged Concrete or Ready Mix for a Footing

A 100 foot run of 16 by 8 inch footing needs about 163 bags of 80 lb mix, or about 218 bags of 60 lb mix, once you include 10 percent waste. Mixing that much by hand or in a small mixer takes hours, and a footing is best poured in one continuous placement so the batches bond. A truck delivers the full amount batched and ready.

Ready mix orders start at 1 cubic yard. Loads of 7 yards or less are short loads with a flat minimum load fee, so a small footing is not billed as a full truck. If the trench is behind a house or the truck cannot get close, ask about concrete pumping in Georgia.

Southern Readymix mixer truck delivering footing concrete to a Georgia job site

Ordering

From Footing Yardage to a Scheduled Delivery

Once you know your cubic yards, call dispatch at (770) 914-9700, Monday to Friday, 8:00 AM to 4:30 PM. Have these ready: the order size in yards, the strength in psi from your plans, the job site address, the day and time you want to pour, and whether a truck can reach the trench or the concrete has to be pumped. If the footing needs an inspection before the pour, say so when you book. Our ready mix concrete delivery page covers the rest of the process.

The concrete footing calculator picks the plant closest to your job site and writes a summary you can read to dispatch. We serve job sites from eight plants across Metro Atlanta and Central Georgia, and the ready mix concrete plants in Georgia page lists each address. Pricing depends on the details of your job, so we quote by phone. The concrete price per yard page explains what shapes your quote.

Before You Pour

What a Footing Calculator Cannot See

A calculator only knows the numbers you give it. It cannot see how far a trench was over-dug, a soft spot that needs more depth, or a stepped footing on a slope. It does not count rebar or where it sits either. Measure the finished trench, not the plan, and order to the next quarter yard so you do not need a second truck and a cold joint.

For a patio, driveway or garage floor, use our concrete slab calculator. For columns and steps, use the full concrete calculator.

Common Questions

Frequently Asked Questions

A 100 foot footing that is 16 inches wide and 8 inches deep needs about 3.29 cubic yards. With 10 percent added for waste and rounded up to the next quarter yard, order 3.75 yards. A 12 by 8 inch footing of the same length needs 2.75 yards.

Multiply the length in feet by the width in feet by the depth in feet to get cubic feet, then divide by 27 for cubic yards. Add about 10 percent for waste and round up. The concrete footing calculator above does it for you from feet and inches.

It depends on the load, the soil and your local code. A common rule of thumb is a footing about twice as wide as the wall it carries. Your plans, engineer or building department set the actual size and depth.

Enter the total wall length, the wall thickness as the width and the wall height as the depth. The calculator then gives cubic yards for the wall. Work out the footing and the wall as two separate calculations.

A 100 foot run of 16 by 8 inch footing takes about 163 bags of 80 lb mix, including 10 percent waste. A truck is usually the easier choice for a continuous footing.

Yes. Orders start at 1 cubic yard, and loads of 7 yards or less are short loads with a flat minimum load fee. Call (770) 914-9700 to schedule your delivery.